Reference and guide to SFIA version 7. Framework status: Development.

#1275 BSMO - proposed wording changes for clarity and readability: change request deferred

From Jim Owens. Details attached below.

Business modelling BSMO

Currently

Suggested Change

Predominantly focused around[1]

Predominantly focused around

Business modelling: Level 5

Currently

Suggested Change

Advises on the choice of techniques and approach

Advises on the choice of techniques and approaches

selecting appropriate techniques and the correct level of detail

selecting appropriate techniques and applying the correct level of detail

about the choice of the modelling approach

about the choice of modelling approach

Gains agreement from subject matter experts to models produced

Gains agreement from subject matter experts on models produced

and gains resolution to resultant issues

and resolves identified issues

Business modelling: Level 2

Currently

Suggested Change

Uses established techniques as directed to model

Uses established techniques, as directed, to model

Develops models with input from subject matter experts and communicates the results back to them for review and confirmation

Develops models under the guidance of subject matter experts.



[1] “Focussed around” is an oxymoron :)